Converting p6 file to ms project1/22/2024 ![]() ![]() ![]() In the first screenshot I have selected a group of projects based on their EPS Node. For this reason I recommend exporting groups of projects based on either a Project Portfolio or EPS node. Caveat: you cannot open more than 100,000 activities concurrently in P6 Professional but there is otherwise no limit to how many projects can be opened at the same time. So the first step is to simultaneously open all of the projects that need to be exported. We all know that a project must be open in order to be exported. ![]() But if the only goal is to move a group of projects from one database to another, there is an easy way to do this very quickly. Backing up a Primavera P6 database is the best option for moving the entire set of project data – schedules, resources, calendars, layouts, etc. ![]()